Article
Author: Tom van der Linden, Solarplaza
In Spain, an optimized 4-hour battery earned 44% of its 2025 revenue in just 37 days. Miss a handful of those days to maintenance or a fault, and the business case takes a serious hit. That figure, shared by S&P Global Energy during our 27 October 2026 webinar 'European BESS: Maximizing profits amid market saturation concerns', captures the shift underway in Europe's battery storage markets: the money is still there, but earning it is getting harder.
Anqi Shi, Principal Analyst for Batteries and Energy Storage at S&P Global Energy, mapped how revenues are evolving across European markets and where saturation is setting in. Nikita Patil, Strategy Manager UK & Ireland at Fluence, then showed how the fine print of battery performance guarantees decides how much of that revenue an asset actually captures.
Key takeaways
Three markets, three business models
S&P Global Energy models battery revenues across Europe, North America, and Asia-Pacific with its Optimal Storage Modeling and Simulation Suite (OSMOSIS). The tool allocates a battery's capacity across energy, ancillary service, and capacity markets to maximize revenue. Shi stressed one assumption up front: the results use historical prices with perfect foresight, so they compare market opportunities rather than predict what a specific asset will earn.
In Europe, the picture is increasingly market-specific. For a 4-hour battery, Great Britain is a mature market where revenue comes from a mix of energy arbitrage, ancillary services, and capacity payments. Germany is a transitional market, with revenue split fairly evenly between ancillary services and energy trading. Spain is still emerging, and ancillary services dominate. During Spain's 2025 blackout, ancillary service prices spiked, pushing revenues far above the other two markets.
High revenue, high risk
At first glance, that makes Spain look like the best market for storage. Shi argued that revenue potential alone doesn't make a market investable. The real question is the quality of those revenues.
S&P ranked each market's daily revenues for an optimized 4-hour battery in 2025 and measured how much came from the top 10% of days, the 37 highest-value days of the year:
In Spain, the challenge isn't finding revenue but capturing it. Missing a few of those days because of maintenance or an unexpected failure can hurt project economics badly. As Shi put it: "The highest revenue market is not always the most bankable market."
Ancillary services are filling up
Great Britain and Germany face a different problem. In both markets, installed battery capacity now exceeds the volume of ancillary services that grid operators procure. Great Britain crossed that line a few years ago, and Germany did so in 2026. The result is much lower ancillary service prices than in Spain. Spain is earlier in the cycle but is likely to face the same pressure over time, a pattern S&P also sees in Texas (ERCOT) and Australia.
The squeeze is set to spread across Europe. Today, installed front-of-the-meter storage in most European markets is below 10% of annual peak demand. By 2030, most markets are expected to reach the level the UK is at today. By 2035, S&P forecasts around 10 markets at 40% to 80%, a level at which batteries compete for wholesale arbitrage as well as ancillary services. Poland, Czechia, Belgium, Finland, and Denmark are close to zero today but could reach 30% to 40% within five years. Ireland and Bulgaria are already at about 20% and still growing, in Bulgaria's case driven by national tenders.
Arbitrage and capacity payments take over
If ancillary services can't absorb battery growth, energy arbitrage has to. S&P's data shows a clear link between renewable penetration and day-ahead price spreads in Great Britain, Spain, and Germany. Its forecast has solar and wind generation growing over the next 10 years while dispatchable generation (gas, coal, hydro, and nuclear) declines. That points to more negative prices during the day, higher evening peaks, and wider spreads for batteries to trade on.
Wider spreads don't solve bankability, though. Banks favor long-term, stable revenue, and the UK capacity market shows how that can work. In the T-4 auction, longer-duration systems earn more, and the gap is growing: in 2024, a 4-hour battery earned about 50% more capacity payment than a 2-hour battery, but from 2027 it earns double. Historically, 2-hour or shorter batteries offered the best returns in the UK. As ancillary service revenue declines and capacity revenue rises, 4-hour systems are becoming the sweet spot, combining contracted income with meaningful merchant upside.
Optimize, position, de-risk
Shi condensed the findings into three strategies for developers and investors:
Her conclusion: "Saturation in Europe does not mean that battery profitability will disappear." It means projects need better optimization and risk management.
What's behind the guarantee number
Revenue forecasts assume the battery performs as designed. Patil turned to what happens when it doesn't. Using a 75 MW, 2-hour Fluence system in Ireland as her example, she framed performance around four questions that every revenue model rests on: can the battery deliver its rated power, for the full duration, at the designed efficiency, and does it degrade as expected?
The industry's three standard guarantees cover availability, round-trip efficiency (RTE), and energy capacity. Every supplier offers them, but Patil warned that what matters is the contractual language behind the number. Fluence's overview of the main performance risks:
| Risk | What it measures | When it shows up | Impact |
|---|---|---|---|
| Availability | Share of power ready to use | Real time | Lost revenue, potential penalties or derating |
| State of charge (SOC) accuracy | Accuracy of the energy available to dispatch | Real time | Lost revenue, potential penalties or derating |
| Imbalance | Differences in SOC across linked cells | Real time | Lost revenue, potential penalties or derating |
| Energy capacity | Energy lost per discharge as the battery degrades | Annual | Lost revenue, potential penalties or derating |
| Round-trip efficiency | Energy lost between charge and discharge | Annual | Higher energy costs |
Availability. Calculation methods differ by supplier, annually or quarterly, and so do exclusions. Grid outages, operator-caused outages, and planned maintenance (typically up to 1%) usually don't count against the guarantee. Even a covered equipment failure can turn a planned 75 MW discharge into 70 MW. With 21% of UK revenue earned on 10% of days, the timing of that failure matters a lot.
SOC accuracy. This was the risk Patil spent the most time on. The battery management system estimates state of charge from cell voltage, but lithium iron phosphate (LFP) batteries have a very flat voltage curve, especially in the middle range where frequency regulation keeps them cycling. Errors build up over time and, unmanaged, can reach 20%. In her example, the system expects 50% SOC but actually holds 46%, so a planned one-hour, 75 MW discharge runs out after 55 minutes, 6 MWh short. Many suppliers handle this with contractual buffers that bar the owner from cycling beyond certain SOC levels, sometimes 15% to 20% of the capacity they paid for. Fluence's answer is a dispatchable energy guarantee, with continuous monitoring and recalibration that avoids taking the system offline.
Imbalance. Cells never sit at exactly the same SOC, because of manufacturing differences or even where the chillers are placed. Since the weakest cell limits the whole set, a 5% imbalance stops discharge while other cells still hold energy, cutting the same trade to 57 minutes. The consequences include imbalance costs, derating by the transmission system operator (TSO), revenue cuts from offtakers, or downtime for manual rebalancing.
Round-trip efficiency. It looks straightforward, but it's the hardest guarantee to fix if it falls short, because efficiency is built into the system design and cabling. It also degrades over time, while many buyers only look at beginning-of-life values.
Energy capacity. Patil advised comparing guaranteed energy capacity rather than state of health (SOH), because a flattering SOH figure can mean the system was overbuilt. Flexible performance guarantees can also give owners more room to vary cycling with market conditions.
Her bottom line: software matters as much as hardware, and performance confidence should come from fleet data and operational track record, not just LDs. As she put it later in the Q&A: "LDs will never bring back your lost revenues."
Questions from the audience
Where would you build today? Shi said she prefers certainty over the highest returns. She pointed to Italy, which combines a strong capacity mechanism through its tender scheme with a fundamental need for storage and remaining merchant upside. From a pure modeling perspective, Germany, as Europe's largest power and storage market, remains very interesting.
Will European BESS be more or less profitable by 2030? It depends on the market, Shi said. In Bulgaria and Romania, national tenders could support so much storage that installed capacity approaches peak demand after 2030, leaving little room for other assets. Great Britain and Germany should still have room for profitable projects. She expects tolling agreements, in which an optimizer pays a fixed fee to operate the asset, to spread across Europe and make projects more bankable. Patil agreed, noting that the early frequency regulation gold rush is over: "It's also a question of how they will be profitable."
What else holds back deployment? Grid connection, according to Shi. Most European grids process applications on a first-come, first-served basis, and queues in Germany and the UK are long. A project planned for 2027 that connects in 2029 or 2030 may face a very different market than the one it was modeled on. Grid operators are discussing ways to prioritize storage. Patil added policy uncertainty, citing Ireland, where the DS3 system services program is ending and repeated delays in replacing it are making developers hesitate.
Will longer durations matter more as markets mature? Yes, Shi said, but with a caveat. Grid operators increasingly want multi-day or seasonal storage of 10 to 24 hours or more, yet S&P's modeling shows merchant revenues alone can't support it in any market. Extra schemes are needed, such as the UK's long-duration storage tender with a cap-and-floor mechanism.
What's the most common mistake developers make with guarantees? Patil said developers often compare suppliers on headline numbers, such as a 97% availability guarantee, without checking what the exclusions mean in practice. Developers also lean too heavily on LDs, which rarely match the revenue lost when a system is down at the wrong moment.
And green hydrogen as long-duration storage? Neither speaker is a hydrogen specialist, but Shi pointed to cost, limited policy support, and the need for stable power in hydrogen production as major hurdles. She sees it as a longer-term option, after 2030 or even 2035.
What it means for owners and investors
Taken together, the two presentations point the same way. As ancillary service markets fill up, value shifts to arbitrage and contracted revenue, concentrating in fewer, higher-value hours. That raises the stakes on two things: the trading strategy that targets those hours, and the hardware and software that ensure the battery delivers when it arrives.
The conversation continues in person at the Solarplaza Seminar BESS Ireland on 26 November 2026 in Dublin and the Solarplaza Summit Energy Storage Germany on 8 December 2026 in Düsseldorf. The full webinar recording and slides are available on solarplaza.com.
To learn more about
the topic beyond this article,join Solarplaza Summit Energy Storage Germany on 8 December, taking place in Düsseldorf.