Where Bulgarian solar and storage projects go wrong

Author: Victor Cordon, Solarplaza

Bulgaria has built solar and storage at a pace few markets can match. That speed has also produced a long list of lessons. At the Solarplaza Summit Bulgaria on 14 October 2026, a lawyer, a constructor, an engineering, procurement, and construction (EPC) contractor, traders, and bankers each described where projects run into trouble. Their stories had one thing in common: the expensive problems usually start long before construction, and they are often avoidable.

Key takeaways

  • A few hours of preliminary checks on land, protected areas, and nearby grid facilities can save months of delays later.
  • Grid connection contracts hide costs and risks, from final connection fees to the separate consumption capacity a co-located battery needs.
  • Battery projects mostly fail at the interfaces between suppliers, so responsibilities and acceptance criteria need to be fixed in the contract before construction starts.
  • Commissioning takes around two months on average for large storage assets, and delays or outages cut directly into revenue.
  • Batteries need active operation and maintenance, so saving on equipment or service contracts puts the whole business case at risk.

Do the homework before you commit

Borislava Piperkova from CMS Law sees the same gap again and again: no preliminary study. Checking whether land sits in a protected area, how close it is to existing grid facilities, and whether it is state or private property takes around three hours of legal work, she said, and can save more time than most developers imagine. Geology and hydrology studies are another common skip, until construction starts and the soil turns out to be unsuitable for panels or a substation, and money goes into foundations that earlier studies would have flagged.

Elena Rasheva from Evklips Energy shared an extreme example from Finland: a 240 MW site where her team initially came back without photos, because 95% of it was bedrock. The project went ahead, and half is now operating, because everyone was involved from the start. She contrasted that with the Netherlands, where congestion paused projects before construction began, and with cases in Bulgaria where construction stopped mid-way over a permit issue, with crews already on site. "Building permit does not give you a ready to build project always," she said.

Piperkova also warned against treating environmental, social, and governance (ESG) requirements as a box ticked by the environmental permit. Lenders and international buyers expect more, such as real engagement with local communities, and it doesn't have to be expensive if it starts early. Appeals by non-governmental organizations, once mainly a wind problem, now affect solar and BESS too, including upgrades at operating plants, so timelines should account for them.

Read the grid contract closely

Grid connections bring their own traps. Developers can now secure a connection at an early stage, but that also means committing, and paying a €25,000 per MW deposit for production units, before the project is certain. In some areas, solar and standalone battery energy storage systems (BESS) have been given the same grid capacity, with no clear rules on which one must stop when. Piperkova expects that to end in a letter from the operator asking one of them to shut down.

The final grid connection fee is another cost that developers tend to underestimate, sometimes because it arrives years after signing. The only way to manage it, she said, is to define the scope of the Electricity System Operator's (ESO) work in the connection contract from the start and take as much of the work on yourself as possible. And co-located batteries do not come with free consumption capacity: it is a separate permit, and without it, the battery may only be able to charge from the solar plant. Existing storage projects are also struggling with imbalances and high reactive energy costs, caused by cheap equipment, installation issues, or poor operation.

The plant fails at the interfaces

Lucian Safta from CJR Renewables focused on standalone BESS, drawing on his company's experience in Chile, where it reports around 80% market share and 800 MW installed, and in Romania. His central message: "A battery project may be procured through several contracts, but it must ultimately be delivered, tested, and accepted as one asset."

Most problems, he said, fall into four zones: site readiness, integration between control systems, gaps in contract scope, and acceptance. He gave three examples. On a six-site portfolio in Romania, screw-pile foundations recovered time after procurement delays, a solution his team proposed by challenging the default design before it was frozen. On another project, each control system passed its own factory test, but the plant struggled in integrated testing because suppliers used different signals and logic. The fix was one master signal matrix and one integrated test approach. "Individual FATs do not prove plant performance," he said, referring to factory acceptance tests. "Only integrated plant testing proves plant performance." In a third case, the plant was technically almost complete but stuck contractually, because the parties disagreed on what counted as successful acceptance.

His advice is to design acceptance backwards, from the final certificate to the contract signature, and to choose the contract structure consciously. Full EPC gives one point of accountability, owner-supplied equipment gives more control over manufacturers, and multi-package contracts give flexibility but the most coordination work. Whatever is removed from one contract shows up elsewhere, usually on the owner's side. For Bulgaria, he recommended a compliance workshop before issuing the tender, turning every local obligation into a design input, a responsible party, a required document, and a schedule milestone.

Commissioning and availability decide revenue

Once a plant is built, the clock is running. Petya Dimova from Enery Energy said commissioning large storage assets has taken around two months on average in recent months, ranging from one to three, as the energy management system, reactive energy, and own consumption get set up. Her advice: don't underestimate this phase, and let the EPC contractor and other specialists do their work instead of pushing to capture yesterday's spreads.

Martin Georgiev from Electrohold Trade put numbers on delays. In his experience, a one-week delay in integrating an asset costs around 2.5% of yearly revenue, and three days of communication outages cost another 1%. Banks notice. Vasil Bachvarov from DSK Bank made the same point from the lender's side: it makes little sense to save €50,000 per year on operations and maintenance (O&M) when a large project can earn €50,000 on a good day. "You cannot make up lost time," he said.

Mariyana Yaneva from IPS International Power Supply, a Bulgarian battery manufacturer, put it plainly. "Batteries are not solar panels. Don't go for the maintenance free catch." No contract structure or liquidated damages clause replaces a team that keeps the system running, she argued, because the asset owner carries the result either way. Rosemary Colaert from Clean Horizon added a smaller but costly item: neighbors. Noise issues can force walls and other measures that push up CapEx.

Rules still coming

A few risks sit just over the horizon. Piperkova warned that cybersecurity rules, not yet fully enforced in Bulgaria, could in a worst case require operating plants to replace their inverters, most of which are Chinese, while bank financing is still running. Standalone BESS currently needs no license, which she doesn't expect to last. And Philippe Macé from the Becquerel Institute noted that many mid-sized developers are not ready for tighter European procurement rules.

None of this is a reason to slow down, the speakers agreed. It is a reason to front-load the work. As Safta put it on his final slide, the lowest risk-adjusted path to commercial operation beats the lowest headline price.

Read our full recap of the Solarplaza Summit Bulgaria 2026 here.