Article

16 November 2026

Bookmark

BESS End-of-life Planning Equipment Reuse Solar PV Asset Management

Five building blocks of a bankable end-of-life strategy

Author: Tom van der Linden, Solarplaza

'In many financing documents, the reserve is fake.' Jan Clyncke, Managing Director of PV CYCLE, did not soften his message at the Recycling Solar & BESS Summit in Amsterdam on 8 October 2026. With repowering, early failures, and new EU rules bringing end-of-life forward, he set out what a 'bankable, audit-proof' end-of-life strategy needs: one that a lender can underwrite, a regulator can audit, and a buyer can verify without taking your word for it.

His answer comes down to five building blocks. Here they are as a checklist you can run against your own portfolio.


Key takeaways

  • A bankable end-of-life strategy rests on evidence, not on intentions in a financial model.
  • Doing it properly costs money, but it is the smallest cost you will face, and the only one you control.
  • The first movers gain the most: their portfolios will clear due diligence faster and sell on better terms.

The checklist

1. A funded, ring-fenced reserve

  • The rule: A real reserve, sized on realistic costs for transport, treatment, substances of concern, and site restoration.
  • The test: Can you show your lender where that money sits today?
  • Red flag: A small decommissioning line in the model, offset by an optimistic scrap value.
  • The payoff: 'The portfolio with a clear, funded, benchmarked reserve will be the one that clears due diligence the fastest.'

2. Complete producer and compliance records

  • The rule: For every asset, record who the producer is, in which country, with which registration, and at which PRO. For batteries, add the digital passport and state-of-health data.
  • The test: Could you answer that for a plant you bought last year?
  • Red flag: A producer that no longer exists, or records you would have to reconstruct at decommissioning.
  • The payoff: A file you assemble at financial close and update over the asset's life, instead of rebuilding it in year 20.

3. Contracted, traceable treatment

  • The rule: Contract permitted treatment operators that work to standards, and require chain-of-custody documentation from your site to final recovery.
  • The test: Do your contracts give you audit rights, and do you use them?
  • Red flag: Subcontracting without your consent, or no explicit ban on exporting untested equipment outside the EU.
  • The payoff: Proof that your panels did not end up on a market in Accra.

4. A deliberate reuse-or-recycle decision

  • The rule: Reuse only with evidence: documented electrical, insulation, and visual tests for panels, and verified state of health and safety assessments for BESS.
  • The test: Would the reuse decision stand up in an audit?
  • Red flag: Pallets labeled 'used, functional' with no test certificate.
  • The payoff: Avoiding a legal cost that 'exceeds the residual value in the product by a wide margin.' When in doubt: 'If the reuse decision cannot be defended in an audit, make it a recycling decision.'

5. Transfer-ready documentation

  • The rule: Keep everything above in a data room, ready for the moment the asset is sold.
  • The test: Could a buyer verify your end-of-life position without calling you?
  • Red flag: End-of-life liability handed over 'with a warranty and a hope.'
  • The payoff: Buyers will start to price this, and Clyncke expects the difference to show in exit multiples.

Who does what

Clyncke closed his keynote with one assignment per group:

  • Asset managers: Audit your portfolio this year. If you cannot name the producer, PRO, reserve, and treatment route for a plant, 'you have found a liability that is not yet on your balance sheet, but it will be.'
  • EPCs: Stop treating end of life as out of scope. Offer decommissioning and recycling as a bankable service with documentation, certified partners, and transparent prices.
  • Investors and lenders: Put end-of-life reserves and compliance documentation into term sheets and due diligence checklists. 'You have more influence over the industry and its behavior than any regulator.'

The last group is already moving. Anouk Blum-den Heijer, Managing Partner at StartGreen Capital, said in the closing panel that end-of-life used to be 'another person's problem' once a loan was repaid. Today, her investors expect no reputational or financial risk, so it enters StartGreen's ESG analysis early in the process.


The cost of waiting

Yes, this costs money, Clyncke acknowledged. He asked the room to compare three numbers: the cost of building the reserve and documentation today, the cost of responding to an enforcement action or failed sale tomorrow, and the cost of being the portfolio that cannot demonstrate compliance when competitors can. The first number is the smallest, and the only one you control.

Read the full overview of the summit in our main report, The line has arrived: takeaways from Recycling Solar & BESS 2026.

Stay on top of the global solar market by joining one of our upcoming events.