Author: Tom van der Linden, Solarplaza
Asked how many of their operating solar plants a battery retrofit makes sense for, 70% of the audience in one Prague session answered: a very large part. The harder question is how to do it when the plant already sells its power under a contract written for solar alone.
At the Solarplaza Summit Asset Management Europe on 27 October 2026, speakers from the advisory, utility, lending, and operations side each covered a piece of that puzzle. Put in order, their advice reads as six steps.
Key takeaways
Step 1: read your PPA before you order anything
Under a typical corporate PPA, the buyer has to approve technical changes to the site. Mikkel Kring of Our New Energy described a Swedish plant with a pay-as-produced PPA, signed two years ago, where the owner now wants to add a battery. The solution was to install a separate solar meter in front of the battery. The buyer is paid based on what the solar plant produces, and the owner keeps the optimization value. "That's a very simple way," Kring said. His advice for contracts still to be signed: make sure the PPA gives you the right to add storage later, "leaving the buyers equally well off."
Step 2: check what your grid connection allows
Thomas Luypaert of Global Infrastructure Partners named the first technical question: "Is it only an export connection, or is it only an import grid connection? That will affect the economics of your batteries quite a lot." A battery that can only charge from its own solar plant is a different asset from one that can also buy from the grid. Claus Wattendrup of Vattenfall plans for both from the start, permitting storage alongside every solar and wind project because "it doesn't add a lot of money" and makes better use of the connection.
Step 3: decide what you are selling
Kring sees three products that solar plus storage can offer corporate buyers:
The third opens the largest pool of demand, because it matches how companies use power. It also carries the most risk, since the seller settles volumes it does not produce in every hour. Kring considers it workable in markets with relatively high prices, such as Denmark, Germany, and Poland, and for owners with more than one project.
Step 4: expect two contracts
The old model had one offtaker doing everything. Kring now expects a split: a bankable counterparty, a utility or a corporate, that provides revenue certainty, and a specialist trader that optimizes the battery on a contract of one to three years. Short terms let you switch if the trader underperforms.
Step 5: build it as one system
"Most of the people are thinking that they're just co-located, two systems in the same fence," said Erman Terciyanlı of inavitas. "Actually, it's one system." He often sees the master controller placed inside the battery system, which makes later changes harder, and stressed that a battery site must coordinate control decisions within 100 milliseconds to comply with grid requirements.
Responsibility needs the same clarity. Marta Valien of Foresight Group asked a contractor how warranties and liability are split between an old solar plant and a new battery on the same site. The answer she got: "We are not there yet." Tatjana Venditti of Econergy uses one O&M (operations and maintenance) operator for the whole site, under the battery's long-term service agreement. Terciyanlı has seen the alternative: with two operators, each blames the other when something fails. Gavin Cornall of Roxtec added the cost argument for getting it right early: fixing a problem after going live costs about "five times".
Step 6: bring your lender along
A battery does not automatically make a plant easier to finance. "If you have a merchant solar farm and then add a merchant battery, it doesn't help with your bank financing," Wattendrup said. Lenders also see something new to assess. "We open up a whole new layer of risk when we have two assets, two SPVs that we have to manage contractually," said Leoni Hartung of Berenberg, referring to special purpose vehicles. Requests for hybrid financing are plentiful, she noted, but "execution is still to be defined."
Kring's own summary fits on one line: keep it simple for the corporate buyer, and make sure your PPAs allow for a battery before you need one.
This article is based on sessions at the Solarplaza Summit Asset Management Europe 2026.